24-hour TSP Monitoring Results
Station CM_WF1a, The Wah Ming House                              
Start Finish Weather Filter Weight (g) Elapsed Time Reading Sampling Time Flow Rate (m3/min) TSP Conc. Action Level Limit Level Observations / Remarks Sampler Filter
Date Time Date Time   Initial Final Initial Final (hrs) Initial Final Average  (µg/m3)  (µg/m3)  (µg/m3)   ID ID
04-Jan-11 08:00 05-Jan-11 08:00 Fine 2.8367 3.0719 1726.76 1750.76 24.00 1.2920 1.2920 1.2920 126 185.3 260 Rock excavation Wah Fu 432
10-Jan-11 08:00 11-Jan-11 08:00 Fine 2.8297 3.0977 1750.75 1774.75 24.00 1.1676 1.1676 1.1676 159 185.3 260 no works in progress Wah Fu 439
14-Jan-11 08:00 15-Jan-11 08:00 Fine 2.7747 3.0639 1774.76 1798.76 24.00 1.1676 1.1676 1.1676 172 185.3 260 no works in progress Wah Fu 446
20-Jan-11 08:00 21-Jan-11 08:00 Fine 2.8218 3.0975 1798.77 1822.77 24.00 1.1620 1.1620 1.1620 165 185.3 260 no works in progress Wah Fu 452
26-Jan-11 08:00 27-Jan-11 08:00 Fine 2.8245 2.9804 1822.77 1846.77 24.00 1.1667 1.1667 1.1667 93 185.3 260 no works in progress Wah Fu 458
                        Min. 93          
                        Max. 172          
                        Average 143